Who carries data-center power risk?

November 12, 2026 | Energy infrastructure

A power strategy is a bundle of delivery dates, minimum payments and risks. The cheapest energy price may not be the lowest-risk commitment.

1 Power is a financial commitment before it is a commodity

A data-center developer is buying more than electricity. It is also making commitments about when the facility will open, how much capacity it will use and who pays if the building, power plant or grid connection arrives late. A low energy price cannot answer those questions.

The scale is real, but the numbers need dates. Lawrence Berkeley National Laboratory estimated U.S. data-center electricity use at 176 terawatt-hours in 2023. Its December 2024 study modeled 325-580 TWh for 2028. That is a scenario range from an older study, not measured 2026 demand or a promise that every proposed campus will be built. 4,5

For business readers, the useful question is narrower: how much of a project's power bill remains payable when its expected load does not arrive?

2 Ohio shows why the fine print matters

Ohio Power's current Schedule DCT, effective August 28, 2026, illustrates the answer. It defines a data center using aggregate monthly maximum demand greater than 25,000 kW, with additional rules for new load, affiliated projects and existing load. Applicability must be checked against the actual facility and agreement. 1

For new load, the initial contract is at least the load-ramp period plus eight years. A ramp can last up to four years. During ramp-up, monthly billing demand is at least 85% of the agreed ramp capacity. After ramp-up, the minimum is not a universal flat 85% of contracted capacity. The tariff uses capacity bands and an 11-month billing-demand lookback. 1

Consider a deliberately simplified 50 MW contract after ramp-up, with no other affiliated new load. The tariff's capacity-band calculation is 15,000 kW + 85% x (50,000 - 25,000), or 36,250 kW. A higher demand lookback can increase the billed amount. Multiplying 50 MW by 85% would instead give 42.5 MW and misstate this particular floor. 1; calculation

Collateral is a second exposure. Subject to the tariff's credit and liquidity tests, new-load customers must provide a guarantee or collateral equal to 50% of total minimum charges over the full contract term. That is a credit-support requirement, not automatically a cash expense of the same amount. Eligible instruments and their cost require separate review. 1

The exit provision is also conditional. The tariff does not offer an unrestricted right to walk away at any time by paying three years of charges. Its example allows a customer with a three-year ramp to use the specified exit route only after year eight. Timing and surviving obligations matter. 1

3 Onsite power changes the risk, not just the meter

A third-party behind-the-meter PPA can leave ownership and operation of the generation plant with a specialist. The buyer still needs to examine minimum payments, performance remedies, backup supply and what happens if either project is late. A&O Shearman's July 2026 analysis identifies the linked financing and stranded-asset risks of these arrangements. 6

Fuel deserves its own line. Bracewell's October 27, 2026 review describes data-center arrangements that resemble tolling: the buyer provides fuel while the generator gives availability and heat-rate guarantees. If fuel procurement moves to the buyer, so do questions about gas price, transportation, fuel quality and delivery failure. The contract must say whether capacity payments continue when fuel is unavailable. 7

Owning the plant or acquiring it through a build-transfer agreement is another structure, not a free upgrade. It brings capital, construction and operating exposure onto the developer's side. A cheaper modeled energy cost can coexist with a larger financing and execution burden. 6; analysis

Nor does backup generation automatically become unrestricted commercial power. EPA identifies federal engine and turbine standards alongside state and local permitting. Its treatment of engines dispatched under specific emergency orders should not be read as general permission for ordinary continuous operation. 9

4 Clean firm power has a different timetable

Utility-mediated procurement offers another route. On February 17, 2026, Ormat announced a portfolio PPA with NV Energy for up to 150 MW supporting Google through the Clean Transition Tariff. The announcement described new projects expected online in 2028-2030 and said the agreement was subject to Nevada regulatory approval at that time. This is an announced structure, not evidence of power available today. Later approval status was not established for this draft. 8

The comparison is therefore among bundles: grid service with capacity commitments; third-party onsite supply; buyer-fueled tolling; owned generation; or utility-mediated clean supply. Each assigns construction, fuel, reliability and credit risk differently. A financial contract or energy attribute alone should not be treated as proof of physical power at a particular site. 6,7; analysis

5 What a useful comparison needs

A practical review starts with the same hourly load and opening-date assumptions for every option. It then puts energy, demand charges, standby service, fuel delivery, maintenance, redundancy, collateral costs and termination payments on separate lines. Delays and low utilization need their own cases, rather than being hidden inside a single average price. 1,6,7; analysis

The result may not identify a universal winner. It should identify the obligations that the developer can support, the ones a partner must take and the ones still awaiting a utility, engineering or legal answer. That is the difference between an attractive price and a workable power strategy.

6 About Xyzenrgy

Contact Xyzenrgy to discuss the energy questions facing your business: [email protected].

Educational reporting and labeled analysis, not a forecast or financial, engineering, tax or legal advice. Sources checked November 12, 2026.